Question

On average, each unit produced by the Kantor Company takes 0.90 worker hours and 0.02 hours of machine time. Furthermore, each worker and machine is available
160 hours a month. Use these planning values and the following sales forecast to estimate (1) The number of worker hours and machine hours needed each month and
(2) The number of workers and machines needed each month.
Round your estimates of the number of workers and machines needed to the nearest whole number.
MONTH SALES FORECAST
October......... 44,000
November......... 52,000
December......... 68,000
January......... 69,000
February......... 58,000
March......... 46,000



$1.99
Sales1
Views65
Comments0
  • CreatedApril 10, 2015
  • Files Included
Post your question
5000