Producing an item requires 6 different tasks. Let tj denote the time (in seconds) to complete task

Question:

Producing an item requires 6 different tasks. Let tj denote the time (in seconds) to complete task j. We have: t1 = 30, t2 = 25, t3 = 35, t4 = 40, t5 = 15, t6 = 30. You would like to divide the tasks to 4 workers to constitute a production line.
a. Find the production capacity of the line for the following assignment: Worker 1 → Task 1, Worker 2→ Task 2, Worker 3→Tasks 3,4, Worker 4 → Tasks 5,6.
b. Find optimal assignment (to maximize the production capacity) if the task sequence should not be broken (task j should be done before task j +1).
c. Find optimal assignment (to maximize the production capacity) if the task sequence can be broken (no precedence relationship between tasks).
Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question
Question Posted: