gantt chart

Project Description:

given the following project to landscape a new building site:

activity duration
(days) immediate
predecessor resource
a 2 none x, y
b 2 a x
c 3 a x
d 4 b, c x, y
e 3 d w, x
f 1 d w, x, y
g 2 e, f x, y

a. draw a gantt chart
b. assuming a 5-day week, find the critical path and project duration in days.
c. given that each resource is assigned 100 percent to each task, identify the resource constraints.
d. identify what alternative solutions can be used to shorten the project duration without over allocating the resources.