Project Description:

2. the following infomation is known about a project

activity activity time(days) immediate predecessor
a 7 -
b 2 a
c 4 a
d 4 b,c
e 4 d
f 3 e
g 5 e

a. draw the network diagram for this project
b. determine the critical path and project duration
c. calculate the slack for each activity.