1. given the following data:
period 1 2 3 4 5 6 7 8 9
gross requirements 70 30 90 30 80 20 90 60 80
the beginning inventory is 0 and there are no scheduled receipts. the order cost is $90 and the holding cost is $1 per part per period.
(a) what are the order costs, carrying costs, and totals cost over the 9 periods using the lot-for-lot size rule?
(b) what are the order costs, carrying costs, and totals cost over the 9 periods using the fixed order quantity rule with foq = 100?
(c) what are the order costs, carrying costs, and totals cost over the 9 periods using the period order quantity rule with poq = 3?
Skills Required:
Project Stats:

Price Type: Fixed

Project Budget: $0 to $10
Completed
Total Proposals: 3
1 Current viewersl
96 Total views
Project posted by:

Proposals

Proposals Reputation Price offered
  • 4.9
    95 Jobs 45 Reviews
    $20 in 1 Day
  • 4.9
    1154 Jobs 609 Reviews
    $15 in 2 Days
  • 4.9
    14 Jobs 9 Reviews
    $10 in 4 Hours