for the network shown in figure p12-24 (page 547 of your textbook), with all times indicating weeks, answer the following questions:
a. what is the impact on the end date of the project if activity b slips by two weeks?
b. what is the impact on the end date of the project if activity e slips by one week?
c. what is the impact on the end date of the project if activity d slips by two weeks?
d. if the customer offered you a bonus for completing the project in sixteen weeks or less, which activities would you focus on first as part of the compression (crashing) analyses?