26. given the information in the following table, draw the aoa network. using the same information, enter the data into msp assuming a seven-day workweek. (to change the calendar in msp from its five-day week default click "help," type "calendar change," and follow directions.) develop the appropriate aon network and gantt chart. using any method you wish, find the critical path and critical time for the network. then find the slack for all activities.



-------
a. construct the network diagram.
b. find each activity's es, ef, ls, and le
c. identify all paths. which path is the critical path?
d. calculate the slack for each activity.
e. how long will it take to complete the project?
Skills Required:
Project Stats:

Price Type: Negotiable

Completed
Total Proposals: 4
1 Current viewersl
12 Total views
Project posted by:

Proposals

Proposals Reputation Price offered
  • 4.8
    405 Jobs 247 Reviews
    $0 in 0 Day
  • 4.8
    232 Jobs 193 Reviews
    $0 in 0 Day
  • 4.9
    287 Jobs 248 Reviews
    $15 in 0 Day