4. wayward freightlines inc., has asked you to determine whether they should purchase a new automatic parcel sorter or whether they should wait to invest their capital. details of three bids that were received are shown in the table below. using the ror analysis, determine which alternative to choose (if any). use a marr of 15%.

ship-r sort-of u-sort-m
useful life, years 7 7 7
first cost $184,000 $235,000 $180,000
salvage value 38,300 44,800 14,400
annual benefit 75,300 89,000 68,000
m&o cost 21,000 21,000 12,000