supply chain management

Project Description:

given the following information for an important purchased part, compute the (a) eoq, (b) total purchase cost, (c) annual holding cost, (d) annual order cost, (e) annual total cost, (f) reorder point, (g) number of orders placed per year and (h) time between orders. use microsoft excel to plot the cost curves (annual holding cost, annual order cost and annual total cost) on the vertical axis, and the order quantity on the horizontal axis.

use microsoft excel to plot the cost curves (annual holding cost, annual order cost and annual total cost) on the vertical axis, and the order quantity on the horizontal axis.
annual requirement = 5,000 units
order cost (s) = $100 per order
holding rate (k) = 20%
unit cost (c) = $20 per unit
lead time (lt) = 6 days
number of days per year = 360 days
Skills Required:
Project Stats:

Price Type: Fixed

Project Budget: $0 to $10
Expired
Total Proposals: 10
1 Current viewersl
66 Total views
Project posted by:

Proposals

Proposals Reputation Price offered
  • 4.8
    548 Jobs 387 Reviews
    $14 in 1 Day
  • 4.9
    348 Jobs 218 Reviews
    $12 in 5 Hours
  • 4.3
    309 Jobs 189 Reviews
    $20 in 16 Hours
  • 4.9
    603 Jobs 384 Reviews
    $10 in 1 Day
  • 4.6
    647 Jobs 468 Reviews
    $10 in 1 Day
  • 4.7
    74 Jobs 28 Reviews
    $10 in 12 Hours
  • 4.9
    1625 Jobs 839 Reviews
    $10 in 1 Day
  • 0.0
    0 Jobs 0 Reviews
    $30 in 2 Days
  • 4.7
    147 Jobs 57 Reviews
    $25 in 1 Day