Recognition of Profit, Percentage-of-Completion In 2010 Gurney Construction Company agreed to construct an apartment building at a

Question:

Recognition of Profit, Percentage-of-Completion In 2010 Gurney Construction Company agreed to construct an apartment building at a price of $1,200,000. The information relating to the costs and billings for this contract is shown below.

image

(a) Assuming that the percentage-of-completion method is used, (1) compute the amount of gross profit to be recognized in 2010 and 2011, and (2) prepare journal entries for 2011.

(b) For 2011, show how the details related to this construction contract would be disclosed on the balance sheet and on the income statement.

Balance Sheet
Balance sheet is a statement of the financial position of a business that list all the assets, liabilities, and owner’s equity and shareholder’s equity at a particular point of time. A balance sheet is also called as a “statement of financial...
Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Intermediate Accounting

ISBN: 978-0470423684

13th Edition

Authors: Donald E. Kieso, Jerry J. Weygandt, And Terry D. Warfield

Question Posted: