Question: Reconsider the Tinker Construction Co. problem presented in Prob. 10.8-1. While in college, Sean Murphy took an OR course that devoted a month to linear
(a) Consider the upper path through the project network. Formulate a two-variable linear programming model for the problem of how to minimize the cost of performing this sequence of activities within 12 months. Use the graphical method to solve this model.
(b) Repeat part (a) for the lower path through the project network.
Step by Step Solution
3.60 Rating (164 Votes )
There are 3 Steps involved in it
a Let x 4 and x C be the reduction in and respectively due to crashing Optimal Solution x A x ... View full answer