Question

Refer again to Problems 14.3 and 14.5, in addition to 100 units of S, there is also a demand for 20 units of U, which is a component of S. The 20 units of U are needed for maintenance purposes. These units are needed in week 6. Modify the net material requirements plan to reflect this change.