Refer to Example 14.1 as the basis for this problem. Meritor hires a team of consultants. The

Question:

Refer to Example 14.1 as the basis for this problem. Meritor hires a team of consultants. The consultants suggest a partial robotic automation as well as an increase in safety stock to 12.5 percent. Meritor implements these suggestions. The result is an increase in efficiency in both the fabrication of muffler assembly and the making of catalytic converters. The muffler assembly fabrication cell now averages 16 assemblies per hour and the lead time has been decreased to two hours’ response time for a batch of 10 catalytic converters. How many kanban cards are now needed?

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Operations and Supply Chain Management

ISBN: 978-0078024023

14th edition

Authors: F. Robert Jacobs, Richard Chase

Question Posted: