Shirley Hopkins is developing a program in leadership training for middle-level managers. Shirley has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table:


(a) Develop an AON network for this problem.
(b) What is the critical path?
(c) What is the total project completion time?
(d) What is the slack time for each individualactivity?