Solve Problem 19.1 except the number of servers at station 2 (CNC milling machines) = 3 and
Question:
Problem 19.1
A flexible manufacturing cell consists of two machining workstations plus a load/unload station. The load/unload station is station 1. Station 2 performs milling operations and consists of one server (one CNC milling machine). Station 3 has one server that performs drilling (one CNC drill press). The three stations are connected by a part handling system that has one work carrier. The mean transport time is 2.5 min. The FMC produces three parts, A, B, and C. The part mix fractions and process routings for the three parts are presented in the table below. The operation frequency fijk = 1.0 for all operations. Determine
(a) Maximum production rate of the FMC,
(b) Corresponding production rates of each product,
(c) Utilization of each machine in the system, and
(d) Number of busy servers at each station.
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Automation Production Systems and Computer Integrated Manufacturing
ISBN: 978-0132393218
3rd edition
Authors: Mikell P.Groover
Question Posted: