Spartan Cabinets is thinking of offering a new line of cabinets. The project activities are as follows:
Question:
a. Identify all the paths through the network and their lengths. Which activities “start” one or more paths? Which activities “end” a path? How will those activities affect ES/EF and LS/LF calculations?
b. Identify all the critical activities and path(s). How long will the entire project take?
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Introduction to Operations and Supply Chain Management
ISBN: 978-0132747325
3rd edition
Authors: Cecil B. Bozarth, Robert B. Handfield
Question Posted: