Students must complete two activities to register for class: registration and payment of fees. Because of individual
Question:
a. Construct a Gantt chart to determine the total time required to process all five students. Use the following sequence of students: D, E, B, C, A.
b. Can you construct a better sequence to reduce the total time required?
c. What problems might be encountered in using this approach to registration in colleges?