After identifying relevant risks, the project team often employs risk-minimization techniques to lessen the probability or impact

Question:

After identifying relevant risks, the project team often employs risk-minimization techniques to lessen the probability or impact of the risk. Match the description/example of the risk mitigation technique with the type of risk being mitigated.
1. Ensure active top management support for the project.
2. Use sensitivity analyst to consider likely alternative benefit levels.
3. Ask Microsoft to demonstrate that its software can meet the system requirements.
4. Give employees adequate incentive to use the new IT.


A. Change risk

B. Project risk

C. Technological risk

D. Solution risk

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Accounting Information Systems

ISBN: 978-1260153156

2nd edition

Authors: Vernon Richardson, Chengyee Chang, Rod Smith

Question Posted: