Lakeside Inc. produces Product A and Product B that require special machining time. Machine time capacity is
Question:
Lakeside Inc. produces Product A and Product B that require special machining time. Machine time capacity is 10,000 machine hours per month. Lakeside estimates April demand for each product and provides additional information as follows:
Required:
Determine how many units of each product Lakeside should produce to maximize contribution margin in April.