Develop cost codes for each element of the WBS shown in Figure 7.4. If you assign the

Question:

Develop cost codes for each element of the WBS shown in Figure 7.4. If you assign the account number 01-00-00 for the overall project, then a good account for the packaging and service area could be 01-01-00, and asphalt paving could be the account 01-01-02.

Figure 7.4