A worker, whose day-work wages are Rs. 25 per hour, received production bonus under the Rowan Scheme.

Question:

A worker, whose day-work wages are Rs. 25 per hour, received production bonus under the Rowan Scheme. He carried out the following work in a 48-hour week:
Job No. 2 was carried out on a machine running at 90 per cent efficiency and an extra allowance of 1/9th of actual time was given to compensate the worker.

4 hours were lost due to power cut. Calculate the earnings of the worker, clearly stating your assumptions for the treatment given by you for the hours lost due to power-cut.

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Cost Accounting

ISBN: 9780070221628

4th Edition

Authors: Jawahar Lal, Seema Srivastava

Question Posted: