A customers order is delivered (received by the customer) on December 1, 2022. This order was placed
Question:
A customer’s order is delivered (received by the customer) on December 1, 2022. This order was placed with the company on September 1, 2022, and received by the manufacturing department on September 15, 2022. Actual production on the order began on October 15, 2022, and was completed November 15, 2022. Based on this information, calculate the following for this order:
(a) Total customerresponse time (CRT),
(b) Order receipt time,
(c) Manufacturing lead (cycle) time,
(d) Manufacturing wait time,
(e) Manufacturing (processing) time,
(f) Delivery time.