The cost of updating an outdated production process is expected to be $81,000 four years from now.

Question:

The cost of updating an outdated production process is expected to be $81,000 four years from now. The equivalent present worth of the update at 6% per year interest is closest to:

(a) $51,230

(b) $55,160

(c) $60,320

(d) $64,160