Mustang Pipeline Co. hired Driver Pipeline Co. to lay 100 miles of pipeline in 98 days. On
Question:
Mustang Pipeline Co. hired Driver Pipeline Co. to lay 100 miles of pipeline in 98 days. On day 58, Driver had only completed 15 miles of pipe and gave up. Realizing that Driver was unlikely to make the deadline, Mustang terminated the contract. Under what principle did Mustang terminate? Was the termination justified?
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Essentials Of Business Law
ISBN: 9781337404198
6th Edition
Authors: Jeffrey F Beatty, Susan S Samuelson
Question Posted: