On April 1, 2015, Dougherty Inc. entered into a cost plus fixed fee contract to construct an electric generator for Altom Corporation. At the contract date, Dougherty estimated that it would take 2 years to complete the project at a cost of $2,000,000. The fixed fee stipulated in the contract is $450,000. Dougherty appropriately accounts for this contract under the percentage-ofcompletion method. During 2015, Dougherty incurred costs of $800,000 related to the project. The estimated cost at December 31, 2015, to complete the contract is $1,200,000. Altom was billed $600,000 under the contract.
Instructions Prepare a schedule to compute the amount of gross profit to be recognized by Dougherty under the contract for the year ended December 31, 2015. Show supporting computations in good form.