The expenditures and receipts below are related to land, land improvements, and buildings acquired for use in

Question:

The expenditures and receipts below are related to land, land improvements, and buildings acquired for use in a business enterprise. The receipts are enclosed in parentheses.

(a) Money borrowed to pay building contractor (signed a note) €(275,000)

(b) Payment for construction from note proceeds 275,000

(c) Cost of land fill and clearing 10,000

(d) Delinquent real estate taxes on property assumed by purchaser 7,000

(e) Premium on 6-month insurance policy during construction 6,000

(f) Refund of 1-month insurance premium because construction completed early (1,000)

(g) Architect’s fee on building 25,000

(h) Cost of real estate purchased as a plant site (land €200,000 and building €50,000) 250,000

(i) Commission fee paid to real estate agency 9,000

(j) Installation of fences around property 4,000

(k) Cost of razing and removing building 11,000

(l) Proceeds from residual value of demolished building (5,000)

(m) Interest paid during construction on money borrowed for construction 13,000

(n) Cost of parking lots and driveways 19,000

(o) Cost of trees and shrubbery planted (permanent in nature) 14,000

(p) Excavation costs for new building 3,000 Instructions Identify each item by letter and list the items in columnar form, using the headings shown below. All receipt amounts should be reported in parentheses. For any amounts entered in the Other Accounts column, also indicate the account title.

Item Land Land Improvements Buildings Other Accounts

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  answer-question

Intermediate Accounting IFRS Edition

ISBN: 9781118443965

2nd Edition

Authors: Donald E. Kieso, Jerry J. Weygandt, Terry D. Warfield

Question Posted: