After securing lease commitments from several major stores, Auer Shopping Center, Inc. was organized and built a

Question:

After securing lease commitments from several major stores, Auer Shopping Center, Inc. was organized and built a shopping center in a growing suburb. The shopping center would have opened on schedule on January 1, 2025, if it had not been struck by a severe tornado in December. Instead, it opened for business on October 1, 2025. All of the additional construction costs that were incurred as a result of the tornado were covered by insurance.


In July 2024, in anticipation of the scheduled January opening, a permanent staff had been hired to promote the shopping center, obtain tenants for the uncommitted space, and manage the property. A summary of some of the costs incurred in 2024 and the first nine months of 2025 follows.image


The promotional advertising campaign was designed to familiarize shoppers with the center. Had it been known in time that the center would not open until October 2025, the 2024 expenditure for promotional advertising would not have been made. The advertising had to be repeated in 2025.


All of the tenants who had leased space in the shopping center at the time of the tornado accepted the October occupancy date on condition that the monthly rental charges for the first 9 months of 2025 be canceled.



InstructionsExplain how each of the costs for 2024 and the first 9 months of 2025 should be treated in the accounts of the shopping center corporation. Give the reasons for each treatment.

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  answer-question

Intermediate Accounting

ISBN: 9781119790976

18th Edition

Authors: Donald E. Kieso, Jerry J. Weygandt, Terry D. Warfield

Question Posted: