Casa Corp. needed a warehouse and maintenance facility on its company site, which already housed three manufacturing/storage

Question:

Casa Corp. needed a warehouse and maintenance facility on its company site, which already housed three manufacturing/storage facilities and the company head office. The lowest outside bid for the facility was $3,200,000. Casa believed that it could successfully construct the facility and have more control over the construction process. Accordingly, it began construction on company owned land in 20X5. The facility was completed in 20X6. Costs related to the project have been accumulated in one account, “manufacturing facility 

Materials ...........................................................................................................................          $1,066,200

Subcontracted work (primarily electrical and plumbing) ..............................................            345,900

Direct labour; idle plant workers assigned to construction tasks .................................           455,800

Direct labour; construction workers hired specifically for this project ............................        123,600

Plant foreman used for construction supervision; salary and benefits ..........................           34,900

Direct labour; plant maintenance workers assigned to construction tasks .......................       53,200

Engineering and architectural services ..................................................................................      216,700


Additional information:

a. Overhead is assigned in the plant to cover supplies used, electricity, occupation costs, maintenance, and so on in the production environment at a rate of $0.57 for every dollar of direct plant labour. This is reasonable for the warehouse project.

b. A loan was negotiated to cover the cash flow needed for construction. Interest of $75,900 was paid on this loan.

c. The administrative office handled the planning and paperwork related to the construction. The staff worked full time on this for approximately six months, representing salary and benefit costs of $57,000.

d. The executive team (chief executive officer and chief financial officer of the company, primarily) devoted approximately 10% of their time to this project during construction. The compensation package for these two individuals was $320,000 for this period.


Required:

1. Prepare a schedule showing the costs that can be capitalized for the building. If any items are not capitalized, explain why not.

2. What, if anything, would change in your answer if the outside bid on this project had been $2,400,000? Explain.

3. Under what circumstances must loan interest be capitalized as part of the cost of self constructed assets? Explain.

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Intermediate Accounting Volume 1

ISBN: 9781260306743

7th Edition

Authors: Thomas H. Beechy, Joan E. Conrod, Elizabeth Farrell, Ingrid McLeod Dick

Question Posted: