Yanmei Construction Company began operations January 1, 2014. During the year, Yanmei Construction entered into a contract

Question:

Yanmei Construction Company began operations January 1, 2014. During the year, Yanmei Construction entered into a contract with Lundquist Corp. to construct a manufacturing facility. At that time, Yanmei estimated that it would take 5 years to complete the facility at a total cost of $4,500,000. The total contract price for construction of the facility is $6,000,000. During the year, Yanmei incurred $1,185,800 in construction costs related to the construction project. The estimated cost to complete the contract is $4,204,200. Lundquist Corp. was billed and paid 25% of the contract price.

Instructions
Prepare schedules to compute the amount of gross profit to be recognized for the year ended December 31, 2014, and the amount to be shown as “costs and recognized profit in excess of billings” or “billings in excess of costs and recognized profit” at December 31, 2014, under each of the following methods.

(a) Completed-contract method.
(b) Percentage-of-completion method.

Show supporting computations in good form.

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  answer-question

Intermediate Accounting

ISBN: 978-1118147290

15th edition

Authors: Donald E. Kieso, Jerry J. Weygandt, and Terry D. Warfield

Question Posted: