a. Given the following master schedule, fill in the projected available and available to promise rows: b.

Question:

a. Given the following master schedule, fill in the projected available and available to promise rows:

On hand: 35 Lot size: 200 Planning time fence: 10 Demand time fence: 2


10 11 12 Period 30 40 40 50 40 40 30 40 40 40 50 40 Forecast Customer Orders Projected Available 35 31 29 21 17 14 33 11


b. A customer wants an order of 100 in period 4. What can you tell him?

c. The customer from part (b) cancels his request, but then says he wants 120 in period 5. What do you tell him now?

d. Sales has requested that you add an MPS of 200 in period 9 to cover their needs for a sales promotion. What do you tell them and why?

e. What action (if any) should be taken in period 11? Why is it okay to take the action?

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  answer-question

Introduction To Materials Management

ISBN: 978-9386873248

8th edition

Authors: Arnold J. R. Tony, Gatewood Ann K., M. Clive Lloyd N. Chapman Stephen

Question Posted: