The standard deviation of demand during the lead time is 100 units. a. Calculate the safety stock

Question:

The standard deviation of demand during the lead time is 100 units.

a. Calculate the safety stock required for the following service levels: 75%, 80%, 85%, 90%, 95%, and 99.99%.

b. Calculate the change in safety stock required to increase the service levels from 75 to 80%, 80 to 85%, 85 to 90%, 90 to 95%, and 95 to 99.99%. What conclusion do you reach?