Refer to E5.6. If Ward, Inc., operates 300 days per year and its lead time is 2

Question:

Refer to E5.6. If Ward, Inc., operates 300 days per year and its lead time is 2 days, what is the reorder point?

Data from E5.6

Ward, Inc., needs 180,000 units each year to meet its production requirements. The costs incurred to place an order are $10 and the cost of carrying a unit in inventory is $2. What is the economic order quantity?