For Gundy Company, units to be produced are 5,000 in quarter 1 and 7,000 in quarter 2.
Question:
For Gundy Company, units to be produced are 5,000 in quarter 1 and 7,000 in quarter 2. It takes 1.6 hours to make a finished unit, and the expected hourly wage rate is $15 per hour. Prepare a direct labor budget by quarters for the 6 months ending June 30, 2020.