A toy firm produces drums sequentially on three machines- A, B, and C-with cycle times of 3,

Question:

A toy firm produces drums sequentially on three machines- A, B, and C-with cycle times of 3, 4, and 6 minutes, respectively.

(a) Determine the optimum efficiency and output rates for adding one, two, ..., six more machines.

(b) Assume now that two identical lines are operating, each with machines A, B, and C. If new machines can be shared between the lines, how should one, two, and then three new machines be added? What are the resulting efficiencies and outputs of the two lines? Is it always best to equally share extra machines between the two lines?

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  answer-question

Operations And Supply Chain Management For MBAs

ISBN: 9781119355328

6th Edition

Authors: Jack R. Meredith, Scott M. Shafer

Question Posted: