On Monday morning, Baxter Industries has the following jobs waiting for processing in two departments, milling and

Question:

On Monday morning, Baxter Industries has the following jobs waiting for processing in two departments, milling and drilling, in that order.


a. Develop a minimum makespan schedule using Johnson’s rule. 

b. Construct a Gantt chart for the minimum makespan schedule.