Question:

Processing times (including setup times) for five jobs that arrived today and are waiting to be processed in the same order on three machines in a shop are given below. Determine the sequence of jobs that will likely minimize the make-span.

Processing Time (hours) Job Machine 1 Machine 2 Machine 3 A 6 3 B 3 5. 4 2 3. 6 D. 3 4 E 2 2