Aliyah Whites political campaign must coordinate a number of necessary activities to be prepared for an upcoming
Question:
Aliyah White’s political campaign must coordinate a number of necessary activities to be prepared for an upcoming election. The following table describes the relationships between these activities that need to be completed as well as estimated times.
a) Develop a project network for this problem.b) Determine the total project completion time and the critical path(s).