Cleaning a toxic landfill took EPA contractor, Henry Garcia, 300 labor-days. If Garcia follows an 85% learning

Question:

Cleaning a toxic landfill took EPA contractor, Henry Garcia, 300 labor-days. If Garcia follows an 85% learning rate, how long will the firm take, in total, to clean the next five (that is, landfills two through six)?