Dorian Furniture Inc., a fictional furniture manufacturer, has established the following production schedule for the next 4
Question:
The two critical work centers for manufacturing these products are sanding and painting. The sanding work center has efficiency and utilization rates of 96% and 92%, respectively. Similarly, the painting work center has efficiency and utilization rates of 92% and 96%, respectively. The time required (in hours) for each furniture product at each work center is given in the following table:
Assuming each work center is available for 40 hours a week, determine the capacity and load profile for each work center for each week.