Shanice Browns gaming software firm has developed the data for a new project, as given in the
Question:
Shanice Brown’s gaming software firm has developed the data for a new project, as given in the following table.
a) What is the critical path? What is the expected completion time of the project?b) What is the probability of all activities on the critical path being completed within 29 days?c) What is the probability of all activities on the other (noncritical) path being completed within 29 days?d) Is it safe to say that the probability of the project being completed within 29 days is equal to your answer from part (b)?