The process of replacing an old tire for customers at Tire Tech.company involves five work elements. The

Question:

The process of replacing an old tire for customers at Tire Tech.company involves five work elements. The table below shows the results of a time study of the process performed by the manager on seven occasions.

a) What is the standard time for the process if the company use an allowance factor of 8%?
b) How many observations are needed to assure 95% confidence level?