What is the late start schedule for a project? a. It is the latest start and the
Question:
What is the late start schedule for a project?
a. It is the latest start and the latest completion times of the project activities so that the overall project is still completed on time.
b. It is a schedule that measures the amount of time an ongoing project is late.
c. It is an accelerated schedule in order to get a project with a late start still completed on time.
d. None of these statements is correct.