The performance of a project was evaluated 10 weeks after its start. Table 15 gives the relevant

Question:

The performance of a project was evaluated 10 weeks after its start. Table 15 gives the relevant information. 

TABLE 15 Activity A B C  E F G H I J Immediate predecessors A A B C F F D, E, G H Normal time 4 2 6 3 10 2 7

a. On the same Gantt chart, show the project plan and the project progress, and discuss the two. 

b. Calculate the SI for each organizational unit U1 and U2 and for the project as a whole. Discuss.

c. Repeat part (b) for the CI. 

d. On the basis of past performance, update the expected completion time and budget. State your assumptions.