Question: 8. Given the planning data for your project, SEMAJ, you have identified the need to use several contractors for three parts of the multiyear project.

8. Given the planning data for your project, SEMAJ, you have identified the need to use several contractors for three parts of the multiyear project. As you determine specific procurement strategies after analyzing the involved WBS elements, your next step is to:

A. Analyze the project scope statement B. Analyze the product description C. Prepare a procurement management plan D. Consider make-or-buy analysis