Critical chain scheduling considers limited resources when creating a project schedule and includes _________ to protect the
Question:
Critical chain scheduling considers limited resources when creating a project schedule and includes _________ to protect the project completion date.
A. reserves B. multitasking C. buffers D. outsourcing