Consider the following activities and their durations. The original project schedule. using early activity starts. is shown
Fantastic news! We've Found the answer you've been seeking!
Question:
Consider the following activities and their durations. The original project schedule. using early activity starts. is shown in Figure 11.20. Reconfigure the network using critical chain project scheduling. What is the critical path? How much slack is available in the noncritical path? Reconfigure the network in Figure 11.20 as a critical chain network. What is the new duration of the roject? How long are the project and feeder buffers?
Activity Duration
A 5 days
B 30 days
C 10 days
D 10 days
E 15 days
Related Book For
Project Management Achieving Competitive Advantage
ISBN: 978-0133798074
4th edition
Authors: Jeffrey K. Pinto
Posted Date: