Following are the three estimates for a project: Task Predecessor(s) Duration (days) Optimistic Most Likely Pessimistic B
Fantastic news! We've Found the answer you've been seeking!
Question:
Following are the three estimates for a project:
Task | Predecessor(s) | Duration (days) | Optimistic | Most Likely | Pessimistic |
B | None | 10 | 9 | 10 | 10.75 |
O | B | 7 | 6 | 7 | 8.2 |
L | B | 4 | 3.8 | 4 | 4.2 |
D | O, L | 8 | 7.5 | 8 | 8.9 |
| | | | | |
Calculate the completion time variance for Task A.
0.274
0.004
0.085
0.054