1. As project manager you discover that a project team member is deliberately charging project time to...
Fantastic news! We've Found the answer you've been seeking!
Question:
1. As project manager you discover that a project team member is deliberately charging project time to the customer but is not performing any work on the customer's project. What do you do?
2. You are a project manager of two projects with the following status.
CPI | SPI | |
Project A | 1.24 | 0.88 |
Project B | 0.98 | 1.20 |
An executive in the organization suggests that you move a two project team members temporarily from Project B to help get Project A back on schedule.
1) Based on the CPI and SPI values what is your response?
2) Are there any additional metrics you would like to see before making a decision?