Question:
(1) What is the code to add an additional array that lists the managers of the individual tasks?
(2) What is the code to add an additional array that lists whether a project was successfully completed on time?
(3) Which method(s) would you add to your program code for the provision stated in Question 2 above?
(4) Using the theory behind this application, i.e. the list - processing procedure, schedule independent tasks of length 8 , 13 , 18 , 14 , 17 ,
7 , 1 , 2 , 19 , 5 , 3 , 7 , 6 , 1 and 2 on three separate processors.
4 | 8 | 12 | 16 | 20 | 24 | 28 | 32 | 36 | 40 | 44 | |
P 1 | |||||||||||
P 2 | |||||||||||
P 3 |
(5) ( Lag and Lead Time )
Consider constructing a flowchart for this application using, MS Visio, for example. Explain how you would flowchart just the procedure for a new method, named showprogress() that will indicate to the user if a task is on - time, running early, or running late.