1. Download the cost baseline template. 2. Use the information below to create a time-scaled network...
Fantastic news! We've Found the answer you've been seeking!
Question:
Transcribed Image Text:
1. Download the cost baseline template. 2. Use the information below to create a time-scaled network diagram (FS = finish-to-start) honoring all dependencies. Assume early start dates for each work package (WP). Outline or highlight the cells to indicate the duration of each work package. Work package one has been done for you as an example. Work Package One Work Package Two Work Package Three Work Package Four Work Package Five Work Package Six Work Package Seven Work Package Eight Work Package Nine Work Package Ten Budget $ 12,000 $5,000 $ 8,000 $ 36,000 $6,000 $ 20,000 $ 2,500 $4,200 $ 3,500 $ 2,400 Duration 4 weeks 2 weeks 8 weeks 9 weeks 3 weeks 8 weeks 5 weeks. 6 weeks 1 week 3 weeks Dependency None None None FS with WP#3 FS with WP#1 FS with WP#2 FS with WP#6 FS with WP#5 FS with WP#8 and FS with WP#7 FS with WP#9 and FS with WP#4 3. Use the budget information above to calculate the weekly budget. Assume a linear relationship between time and money. For example, if a work package was three weeks and has a total budget of $3,000, the weekly budget would be $1,000 (3 x $1,000 = $3,000). 4. There is one row for every work package. The time-scale is in weeks represented as "W1,W2, etc." for week 1, week 2, etc. in the column headers. 5. Calculate the weekly incremental budget for each work package and place it in the correct week based on dependencies and work package durations. 6. Calculate the project's weekly incremental costs and place the total in the "incremental costs" cell for each week (column). 7. Calculate the project's cumulative budget to-date for each week and place in the "cumulative costs" cell for each week (column). 8. Answer the questions related to the completed assignment. 9. Once complete, submit your assignment as instructed. Work Package One Work Package Two Work Package Three Work Package Four Work Package Five Work Package Six Work Package Seven Work Package Eight Work Package Nine Work Package Ten Incremental costs Cumulative costs W1 W2 W3 W4 W5 W6 W7 W8 W9 W10 W11 W12 W13 W14 W15 W16 W17 W18 W19 W20 Total project budget is: Week with highest incremental cost: How many weeks have exactly two work packages planned? At which week does the cumulative budget first exceed $40,000? At which week is the incremental budget exactly $4,200? 1. Download the cost baseline template. 2. Use the information below to create a time-scaled network diagram (FS = finish-to-start) honoring all dependencies. Assume early start dates for each work package (WP). Outline or highlight the cells to indicate the duration of each work package. Work package one has been done for you as an example. Work Package One Work Package Two Work Package Three Work Package Four Work Package Five Work Package Six Work Package Seven Work Package Eight Work Package Nine Work Package Ten Budget $ 12,000 $5,000 $ 8,000 $ 36,000 $6,000 $ 20,000 $ 2,500 $4,200 $ 3,500 $ 2,400 Duration 4 weeks 2 weeks 8 weeks 9 weeks 3 weeks 8 weeks 5 weeks. 6 weeks 1 week 3 weeks Dependency None None None FS with WP#3 FS with WP#1 FS with WP#2 FS with WP#6 FS with WP#5 FS with WP#8 and FS with WP#7 FS with WP#9 and FS with WP#4 3. Use the budget information above to calculate the weekly budget. Assume a linear relationship between time and money. For example, if a work package was three weeks and has a total budget of $3,000, the weekly budget would be $1,000 (3 x $1,000 = $3,000). 4. There is one row for every work package. The time-scale is in weeks represented as "W1,W2, etc." for week 1, week 2, etc. in the column headers. 5. Calculate the weekly incremental budget for each work package and place it in the correct week based on dependencies and work package durations. 6. Calculate the project's weekly incremental costs and place the total in the "incremental costs" cell for each week (column). 7. Calculate the project's cumulative budget to-date for each week and place in the "cumulative costs" cell for each week (column). 8. Answer the questions related to the completed assignment. 9. Once complete, submit your assignment as instructed. Work Package One Work Package Two Work Package Three Work Package Four Work Package Five Work Package Six Work Package Seven Work Package Eight Work Package Nine Work Package Ten Incremental costs Cumulative costs W1 W2 W3 W4 W5 W6 W7 W8 W9 W10 W11 W12 W13 W14 W15 W16 W17 W18 W19 W20 Total project budget is: Week with highest incremental cost: How many weeks have exactly two work packages planned? At which week does the cumulative budget first exceed $40,000? At which week is the incremental budget exactly $4,200?
Expert Answer:
Related Book For
Posted Date:
Students also viewed these accounting questions
-
Managing Scope Changes Case Study Scope changes on a project can occur regardless of how well the project is planned or executed. Scope changes can be the result of something that was omitted during...
-
Case Study: Quick Fix Dental Practice Technology requirements Application must be built using Visual Studio 2019 or Visual Studio 2017, professional or enterprise. The community edition is not...
-
Planning is one of the most important management functions in any business. A front office managers first step in planning should involve determine the departments goals. Planning also includes...
-
Please watch the video link and answer the following questions. https://youtu.be/VtvjbmoDx-I On January 22,1984, Apple produced one of the most famous Super Bowl ads of all time. Directed by Ridley...
-
A 0.300 kg sample is placed in a cooling apparatus that removes energy as heat at a constant rate of 2.81 W. Figure gives the temperature Z of the sample versus time t. The temperature scale is set...
-
True or False. The potential and kinetic energies of a multi-degree-of-freedom system are always quadratic functions.
-
On January 1, 2018, Ranier, Inc., issued \(\$ 300,000\) of ten percent, 15 -year bonds for \(\$ 351,876\), yielding an effective interest rate of eight percent. Semiannual interest is payable on June...
-
1. Describe and evaluate what Charles Schwab is doing. 2. How might the companys culture of not buying into hype and not taking excessive risks affect its organizational structural design? 3. What...
-
At the beginning of December, XYZ Company employed a contractor to cut enough trees to meet the expected demand for Christmas trees. They sell these trees to a local wholesaler in batches of 100....
-
Suppose that you are planning for retirement. You want to have exactly $4 million dollars when you retire. You just turned 26 and plan to retire on your 65th birthday. For the next 15 years, you can...
-
Assets ($'mn) Cash 29-day T-bills 270-day Commercial Paper 2-year Corporate Bond 15-year T-Bond 25-year ARM (reset quarterly) $1,000 Total assets 8,570 9,555 4,457 900 2.705 Liabilities and Equity...
-
Suppose a company is expected to pay a dividend of $12.24 next year. The dividend is expected to grow at 8.67% each year. If the stock is currently selling for $271.95, what is the required rate of...
-
The long - term liability section of Nelson Corporation's balance sheet as of December 3 1 , 2 0 2 3 , included 5 % bonds having a face amount of $ 8 0 0 , 0 0 0 and a remaining discount of $ 1 2 0 ,...
-
Bradley Company sells a product that has variable costs of $52 each and a sales price of $77 each. Bradley has fixed costs of $105,000 and a desired profit of $30,000. If the Company is able to...
-
XYZ, Inc. just paid dividend of $18.42. The dividends are expected to grow at 3.03% each year forever. The required rate of return on the stock is 15.61%. What is today's price of the stock?
-
game tree. a) Consider the following part of a two-player node? 2 What will be the value of the top MAX MAX MIN
-
Halley's comet travels in an ellipti- cal orbit with a = 17.95 and b = 4.44 and passes by Earth roughly every 76 years. Note that each unit represents one astronomical unit, or 93 million miles. The...
-
Download the spreadsheet Ch10Ex02 and import the worksheets to create the database shown in Figure 10-23.Create a report that lists the number of security incidents reported by each department....
-
What steps do organizations take when they decide to buy rather than build software? What activities occur in each step? How is an RFI different from an RFP? Does the logical approach to systems...
-
What are the advantages and disadvantages of custom-building software?
-
A pictorial or graphical representation of the overall flow of work, documents, and operations in an application system is shown in a(n) ( _____________ ). (a) IPO chart (b) forms distribution chart...
-
Which of the following items would be most useful in analyzing the separation of duties and functions in an application system? (a) document flowchart (b) program flowchart (c) HIPO chart (d) source...
-
An important omission from flowcharts and matrix techniques is ( ___________________ ). (a) the ability to represent decisions (b) the ability to include internal control considerations (c) the...
Study smarter with the SolutionInn App